The Ministry of Housing Communities and local government has written draft legislation proposed to come into force 1st June 2020 titled ‘The Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020’ Click here.

Landlords will need to ensure that the electrical safety standards are met  and ensure every electrical installation is inspected and tested at regular intervals of no more than 5 year by a qualified person

First inspection and testing must be carried out before the tenancy commences or by 1st April 2021 in relation to an existing specified tenancy.

Financial penalties faced by landlords for a breach of the above regulations will be a maximum of £30,000

This will need to be passed by the House of Commons and the Lords, but with the new government majority is unlikely to meet much resistance.

David Cox, Chief Executive, ARLA Propertymark commented:

“We are supportive of this concept and believe it will create a level playing field for all agents and landlords as well as ensuring improved safety standards for tenants. Mandating  electrical testing should have a limited impact on good professional landlords and agents in the market, many of whom already voluntarily undertake these inspections. We did raise concerns about the number of engineers available to undertake these reports by the April 2021 deadline but have received assurances from MHCLG about capacity in the supply chain.”

Duties of private landlords in relation to electrical installations

3.—(1) A private landlord(7) who grants or intends to grant a specified tenancy must—

(a)ensure that the electrical safety standards are met during any period when the residential premises(8) are occupied under a specified tenancy;

(b)ensure every electrical installation in the residential premises is inspected and tested at regular intervals by a qualified person; and

(c)ensure the first inspection and testing is carried out—

(i)before the tenancy commences in relation to a new specified tenancy; or

(ii)by 1st April 2021 in relation to an existing specified tenancy.

(2) For the purposes of sub-paragraph (1)(b) “at regular intervals” means—

(a)at intervals of no more than 5 years; or

(b)where the most recent report under sub-paragraph (3)(a) requires such inspection and testing to be at intervals of less than 5 years, at the intervals specified in that report.

(3) Following the inspection and testing required under sub-paragraphs (1)(b) and (c) a private landlord must—

(a)obtain a report from the person conducting that inspection and test, which gives the results of the inspection and test and the date of the next inspection and test;

(b)supply a copy of that report to each existing tenant of the residential premises within 28 days of the inspection and test;

(c)supply a copy of that report to the local housing authority within 7 days of receiving a request in writing for it from that authority;

(d)retain a copy of that report until the next inspection and test is due and supply a copy to the person carrying out the next inspection and test; and

(e)supply a copy of the most recent report to—

(i)any new tenant of the specified tenancy to which the report relates before that tenant occupies those premises; and

(ii)any prospective tenant within 28 days of receiving a request in writing for it from that prospective tenant.

(4) Where a report under sub-paragraph (3)(a) indicates that a private landlord is or is potentially in breach of the duty under sub-paragraph (1)(a) and the report requires the private landlord to undertake further investigative or remedial work, the private landlord must ensure that further investigative or remedial work is carried out by a qualified person within—

(a)28 days; or

(b)the period specified in the report if less than 28 days,

starting with the date of the inspection and testing.

(5) Where paragraph (4) applies, a private landlord must—

(a)obtain written confirmation from a qualified person that the further investigative or remedial work has been carried out and that—

(i)the electrical safety standards are met; or

(ii)further investigative or remedial work is required;

(b)supply that written confirmation, together with a copy of the report under sub-paragraph (3)(a) which required the further investigative or remedial work to each existing tenant of the residential premises within 28 days of completion of the further investigative or remedial work; and

(c)supply that written confirmation, together with a copy of the report under sub-paragraph (3)(a) which required the further investigative or remedial work to the local housing authority within 28 days of completion of the further investigative or remedial work.

(6) Where further investigative work is carried out in accordance with paragraph (4) and the outcome of that further investigative work is that further investigative or remedial work is required, the private landlord must repeat the steps in paragraphs (4) and (5) in respect of that further investigative or remedial work.

(7) For the purposes of sub-paragraph (3)(e)(ii) a person is a prospective tenant in relation to residential premises if that person—

(a)requests any information about the premises from the prospective landlord for the purpose of deciding whether to rent those premises;

(b)makes a request to view the premises for the purpose of deciding whether to rent those premises; or

(c)makes an offer, whether oral or written, to rent those premises.

Remedial action

Duty of local housing authority to serve a remedial notice

4.—(1) Where a local housing authority has reasonable grounds to believe that, in relation to residential premises situated within its area, a private landlord is in breach of one or more of the duties under regulation 3(1)(a), (1)(b), (1)(c), (4) and (6), and the most recent report under regulation 3(3) does not indicate that urgent remedial action is required, the authority must serve a remedial notice on the private landlord.

(2) A remedial notice must—

(a)specify the premises to which the notice relates;

(b)specify the duty or duties that the local housing authority considers the private landlord has failed to comply with;

(c)specify the remedial action the local housing authority considers should be taken;

(d)require the private landlord to take that action within 28 days beginning with the day on which the notice is served;

(e)explain that the private landlord is entitled to make written representations against the notice within 21 days beginning with the day on which the notice is served;

(f)specify the person to whom, and the address (including if appropriate any email address) to which, any representations may be sent; and

(g)explain the effect of regulations 11 and 12, including the maximum financial penalty which a local housing authority may impose.

(3) The local housing authority must serve a remedial notice within 21 days beginning with the day on which the authority decides it has reasonable grounds under paragraph (1).

(4) The local housing authority must consider any representations made under paragraph (2).

(5) Where a private landlord makes written representations the remedial notice is suspended until the local housing authority has complied with paragraphs (4) and (6).

(6) The local housing authority must—

(a)inform the private landlord in writing of the outcome of the consideration under paragraph (4) within 7 days beginning with the day on which the period under sub-paragraph (2)(e) expires; and

(b)where the outcome of the consideration under paragraph (4) is to confirm the remedial notice, confirm that notice and inform the private landlord in writing that the remedial notice is confirmed and the suspension under paragraph (5) ceases to have effect.

(7) The local housing authority may withdraw the remedial notice at any time.
Duty of private landlord to comply with a remedial notice

5.—(1) Where a remedial notice is served on a private landlord, the private landlord must take the remedial action specified in the notice within—

(a)where no representations are made under regulation 4(2) and the remedial notice is not withdrawn, the period specified in regulation 4(2)(d); or

(b)where representations are made under regulation 4(2) and the outcome of the consideration under regulation 4(4) is to confirm the remedial notice, 21 days from the day on which the private landlord is informed that the suspension under regulation 4(5) ceases to have effect.

(2) A private landlord is not to be taken to be in breach of the duty under paragraph (1) if the private landlord can show they have taken all reasonable steps to comply with that duty.

(3) For the purposes of paragraph (2), where a private landlord is prevented from entering the residential premises to which the duty under paragraph (1) relates by the tenant or tenants of those premises, the private landlord will not be considered to have failed to have taken all reasonable steps to comply with the duty under paragraph (1) solely by reason of a failure to bring legal proceedings with a view to securing entry to the premises.
Power of local housing authority to arrange remedial action

6.—(1) Where a local housing authority is satisfied, on the balance of probabilities, that a private landlord on whom it has served a remedial notice is in breach of the duty under regulation 5(1), the authority may, with the consent of the tenant or tenants of the premises in relation to which the remedial action is to be taken, arrange for an authorised person to enter those premises to take the remedial action specified in the remedial notice.

(2) Before the remedial action is taken the local housing authority must serve a notice on the private landlord specifying—

(a)the premises in relation to which the remedial action is to be taken by the authorised person under paragraph (1) and the nature of that remedial action;

(b)the power under which the remedial action is to be taken by the authorised person in paragraph (1);

(c)the date when the remedial action will be taken by the authorised person; and

(d)the right of appeal under regulation 7 against the decision of the authority to arrange for an authorised person to take the remedial action.

(3) The local housing authority must arrange for an authorised person to take the remedial action within 28 days of—

(a)the end of the notice period in regulation 7(3) where there is no appeal; or

(b)an appeal decision that confirms or varies the decision of the local housing authority where there is an appeal.

(4) An authorised person must—

(a)give not less than 48 hours’ notice of the remedial action to the tenant or tenants of the residential premises on which it is to be taken; and

(b)if required to do so by or on behalf of the private landlord or tenant or tenants, produce evidence of identity and authority.

Financial penalties for breach of duties

11.—(1) Where a local housing authority is satisfied, beyond reasonable doubt, that a private landlord has breached a duty under regulation 3, the authority may impose a financial penalty (or more than one penalty in the event of a continuing failure) in respect of the breach.

(2) A financial penalty—

(a)may be of such amount as the authority imposing it determines; but

(b)must not exceed £30,000.


Share This Article


Comments

Seething Landlord

23:21 PM, 15th January 2020, About 4 years ago

Reply to the comment left by Dylan Morris at 15/01/2020 - 22:53
The 18th edition is specified as the standard in the draft regulations - so yes, it appears that if the regulations pass into law unchanged the installation will have to comply with that standard.

MCHLG have apparently said that is not what they intend so there may be changes. If not, we are probably in for another tsunami of unintended consequences.

B4lamb

10:10 AM, 16th January 2020, About 4 years ago

Obfuscated Data

Beaver

10:26 AM, 16th January 2020, About 4 years ago

Reply to the comment left by Seething Landlord at 15/01/2020 - 23:21
Depending upon how the regulations are implemented the unintended consequences could include responsible landlords having to evict their tenants in order to get re-wiring done. And if there's a shortage of rental property many of those tenants would be housed by landlords whose properties aren't compliant because they don't give a **** about the regulations.

Simon Williams

11:36 AM, 16th January 2020, About 4 years ago

My experience of getting a full EICR for a property last year is that this is going to be very costly for most landlords. This 3 bedroom Edwardian flat cost me £3500 to sort out despite having, in lay-man's terms, normal modern-looking wiring and fuse boards etc. I am sure this experience will be common for 100's of thousands of rental properties.
Therefore, in my view, the implementation period is totally unrealistic and will lead to a real shortage of electricians qualified to do the job. Excessive demand for electricians will merely push their prices up.
Serving the full report on every new tenant will be a major headache. They usually run into 20 pages. I will have to do it electronically and hope the courts accept that as good service or it permits for copies in the legislation.
The RLA as usual, let landlords down, by failing to be more robust about the huge challenges landlords will have to face on top of everything else. And if these changes are so vital to protect life and limb, why oh why are they not required in other types of tenure?

B4lamb

13:27 PM, 16th January 2020, About 4 years ago

Obfuscated Data

Rob Crawford

13:46 PM, 16th January 2020, About 4 years ago

Reply to the comment left by Seething Landlord at 15/01/2020 - 09:38
Hi, where have you read that the wiring must be compliant with 2018 regs?

Rob Crawford

13:47 PM, 16th January 2020, About 4 years ago

Hi, where have you read that the wiring must be compliant with 2018 regs?

Seething Landlord

15:07 PM, 16th January 2020, About 4 years ago

Reply to the comment left by Rob Crawford at 16/01/2020 - 13:46
In the draft regulations:
Interpretation
2.In these Regulations—
“electrical safety standards” means the standards for electrical installations in the eighteenth edition of the Wiring Regulations, published by the Institution of Engineering and Technology and the British Standards Institution as BS 7671: 2018
3.—(1) A private landlord who grants or intends to grant a specified tenancy must—
(a)
ensure that the electrical safety standards are met during any period when the residential premises are occupied under a specified tenancy

Beaver

15:37 PM, 16th January 2020, About 4 years ago

Reply to the comment left by Seething Landlord at 16/01/2020 - 15:07
That's not going to result in people having secure long-term tenancies then 🙂

I just told my tenants they could stay another year (although I did put the rent up a bit to cover the extra obligations that have been imposed on me as a landlord, none of which are my fault. But next year it may be....

"...sorry Mr. and Mrs. Tenant, your present tenancy ends in February 2021 but you and your three children must leave by the end of March 2021 at the latest because of the electrical installations, even though as a responsible landlord I had a full EICR done before first letting the property and it wasn't a legal requirement when I did it. The reason you are having to leave is because whilst my house appears to be safe and I addressed everything legally required in the EICR (plus a bit more), as an old house the wiring does not meet the letter of the law according to the 2018 regulations. That means you lose your home, sorry, not my fault....just one of those unintended consequences of new regulations...talk to your MP."

Whiteskifreak Surrey

17:39 PM, 16th January 2020, About 4 years ago

Reply to the comment left by JJ at 16/01/2020 - 15:37
Perhaps we all should write to oir MPs saying that evictions are imminent.

1 2 3 4 5 6 7 8 9 10 11 12 13 17
Landlord Tax Planning Book Now